See the attached pic.
- The sheet is set for 24hr workdays. Mon-Fri.
- There are 2 tasks. one with duration 7d and one with duration e7d.
- The e7d task does not display 7 days of working. The gantt chart bar does not show sunday as a working day.
- Resource view DOES show sunday as a working day.
Bug?
Also, the "roll-up" on the resource view shows some days at 200% and some days at 100%... which is correct, but the rollup is shifted 1 day out of position. It doesn't agree with the detail numbers underneath.
Bug?