Dates start flashing after updating another task's predecessors
Comments
-
@riversofbelief Thank you - your fix solved the issue for me!
-
I encountered the problem of flashing rows when adding dependencies. There didn't seem to be any circular reference error.
Solution - I saved my sheet and refreshed. The refresh made the flashing rows stop flashing.
-
That did not work for me
-
I may have found the issue. I had the same problem and it appears that it was being caused by having a child activity that has no duration in the duration column. Once I entered a duration in the last (or latest) activity flashing it all stopped and cascaded all dates.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives