Formulas
I'm trying to move an excel project timeline to the Gaant template. I currently calculate my dates backwards from the desired in stock date. I've put in my duration for each step, but wanted to know how i can set aformula to deduct the duration days from the in stock date, rather than inputting a start and end date manually?
Tags:
Comments
-
Can you provide a screenshot or some column names? From the sound of it, you should be able to use:
-
What you want a reverse or work-back schedule.
See this post for more:
Craig
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 143 Just for fun
- 59 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!