Sign in to join the conversation:
Hello,
How do I get my % data to roll up to 100?
Its looking like all of the data is running up to 1.
Does that make sense?
Sorry for the hopefully easy questions.
Thanks
- Alex
Format the column to %
(4th from the right on the Format Bar)
I did this. Nothing changed.
You still see 0.36 instead of 36%?
The [% Complete] column treats 0-1 as 0-100%
Craig
That is correct.
I figured it out. I needed to select the % format.
D'OH!
Thanks,
Alex
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…