Hello,
How do I get my % data to roll up to 100?
Its looking like all of the data is running up to 1.
Does that make sense?
Sorry for the hopefully easy questions.
Thanks
- Alex
Format the column to %
(4th from the right on the Format Bar)
I did this. Nothing changed.
You still see 0.36 instead of 36%?
The [% Complete] column treats 0-1 as 0-100%
Craig
That is correct.
I figured it out. I needed to select the % format.
D'OH!
Thanks,
Alex
I have a Smartsheet automation setup to reminder the planning to complete their sections. It is setup to remind weekly until completed box is checked. They received 2 reminders and then the reminders stopped. Any idea what could be wrong? I can't tell that anything has changed in the sheet. Thanks Freda
I'm editing formulas in a Sheet Summary. However, I'm prevented from seeing the formula by an annoying "helpful" popup that obscures my view. I can't figure out how to get rid of the popup. Does anyone know?
I am trying to create a workflow and for some reason it gives me an error with the email I entered as the recipient for my Alert. It is an email that I know works, it is shared to the sheet, and the access to the sheet is unrestricted. I am perplexed at what the issue is. Anyone else get this and know what the issue is?