I am planning a project, so the exact start time is unknown yet.
I'd like to setup it so that I could change the start date once the project is approved, and have all the sequences/tasks updated.
Use Dependencies.
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
First task would be "Project Start" or "Contract Award" or some such.
Craig
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…