I am planning a project, so the exact start time is unknown yet.
I'd like to setup it so that I could change the start date once the project is approved, and have all the sequences/tasks updated.
Use Dependencies.
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
First task would be "Project Start" or "Contract Award" or some such.
Craig
This discussion was created from comments split from: Change Permissions for Specific Items in Workspace.
Hi! I have a sheet that has two form that feed into it. This is to report on Closures due to Staffing, Weather, and Facilities. One team submits closures for Staffing and Weather, while another team only submits Facilities. When I created this set up I have it so the one team gets asked "Reason?" then they can select…
Recently, I got an inquiry if there was any changes or update made in Smartsheet that made the lay out of the email notification change. Specially the Details part. It use to be on a vertical layout but recently we were seeing that it became horizontally. Is this a recent update with Smartsheet?