I am planning a project, so the exact start time is unknown yet.
I'd like to setup it so that I could change the start date once the project is approved, and have all the sequences/tasks updated.
Use Dependencies.
https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
First task would be "Project Start" or "Contract Award" or some such.
Craig
How can I delete old sheets I no longer use from my account?
We want to implement single-sign-on at work and have received approval. However, our IT department wants all external partners to have/use Mayo credentials to log into Smartsheet. Not all of our external partners ever set foot on our campus and don't have our company credentials. I have a couple of questions. Has any other…
I can create a Chart in Dashboard from sheet well but from Report is not working now. I just try with simple Report (just contain 2 column Primary and Number) but cannot make the chart. Is there any changes recently right, because I haven't worked with Smartsheet dashboard for a long time and I remembered that I could do…