I am wanting a formula for new hires to be based off their hire date and to generate a date that would be 30 days after they are hired following on the 1st of the month.
So you want to go forward 30 days, and then the 1st of the month following those 30 days? I just want to make sure I'm clear, so we can get you the most accurate solution.
yes that is correct.
And is that 30 working days or 30 calendar days?
Is there an answer on this? Im also looking for a formula for the first of the month after 30 working days
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…