Manual start date with dependency
Hi.
Im tyring to implement Task B only being able to commence after the completion of Task A while being able to maintain its dependency on Task A and filling in a manual start date for Task B.
So for example
Task A completed January 1
Task B Can start anytime after January 1
Task B Start date can be entered manually
Task B remains dependent on completion of Task A
My problem is if I enter a manual start date for Task B, its dependency on Task A is deleted.
Thanks for your help.
Jason
Comments
-
unfortunately with dependencies enabled, what you are wanting to do is not currently possible in Smartsheet.
While having dependencies enabled can be a very helpful tool, it does drastically reduce the flexibility of your sheet.