Predecessor Error
I keep getting errors for my predecessors in some areas. I cannot replicate it or see what the issue is. I've read a few other forum queries that mention that you cannot refer to a parent row, but sometimes this actually works for me (in fact it is nice that it works because it's easier than using a bunch of child row predecessors to denote when a group of items has completed for a new line to begin.
However, in this case, it is a child row and I'm getting the #REF error even upon reloading the page. Please see a screenshot attached of me trying to refer to row 482 and then it showing an error when I do.
Comments
-
Have you checked the other predecessors for rows 457 and 461. It may be that somewhere along the line there is some circular mess somewhere. I occasionally run into that issue with large project plans requiring multiple predecessors all over the sheet.
-
You're right it was a circular reference about 5 predecessors out due to a wonky project not following the usual process.
Thank you!
-
-
I have the same problem. How to fix it ?
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 219 Industry Talk
- 457 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives