I have imported a checklist from excel, set it up as a Gantt (transposed columnar hierarchy,) put in predecessors, and durations. No bars appear on the chart. What's up with that?
Hugh As your sheet is based on an import and conversion from Excel.....
i'd check your column properties especially your Start and Finish dates columns and do a little due diligence, there must be a small error you haven't spotted?
Good luck!
Richard R
Despite due diligence to this point, including asking this question, I'm quite sure that the issue is on my end. I do have start and end dates set as date type. Is there a list of required columns and settings for a Gantt Chart?
This article explains how to add a Gantt chart to a current sheet. Hopefully, this will help!
https://help.smartsheet.com/articles/765675-work-with-gantt-chart
Hello, I have two sheets. One is "Current tasks" and one is "Completed tasks". I have the rows (individual tasks) auto number when entered (2026-001, 2026-002, etc.). When the row is marked complete, it is moved to the "Completed task" sheet. The problem I am having is that when the row is moved the other tasks that remain…
Its very frustrating when you are adding multiple columns and having to use the slide bar to move to the end and then click the 3 dots and add another column. Seems there has to be an easier more productive way.
I'm receiving this message every time I try to open my sheets. I'm the only admin user. I have already performed proper troubleshooting, such as clearing the cache, logging in incognito, and logging out and back in, but the issue remains unresolved. It's been a few days, and I'm unable to track our projects and this…