Parent rows don't seem to calculate total duration correctly
I am working on a sheet with many sub sections.
I noticed that the parent row total durations seem to be far higher than the durations of the child rows within them.
I assumed they must be pulling data for too many rows, but when I collapse the section the correct rows disappear.
Any suggestions?
Comments
-
Hi,
That is like it should be because the duration on the parent is for the whole section/project and from start to end with consideration to the working days setting in the Project Settings.
In Briefs, it's 101d because the earliest date is 23/07/19 and the latest is 10/12/19, and that's approximately 101 working days.
I hope this helps you!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:[email protected] | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.