HI, If a checkbox is selected in column "SNAGS" can another column "DATE RECORDED" automatically populate the date in which the checkbox field was selected?RegardsStuart
Try this:
=IF(SNAGS1 = true, TODAY(), "")
If you uncheck the box, the date will be cleared.
Unfortunately, that won't probably work because the TODAY will update to the present day.
The only way that I can see that it would work will be if you change the date manually to the date on that day.
Best,
Andrée
Hi again Stuart,
It's possible to set up with the help of a service like Zapier, Azuqua or similar. Depending on your specific use case the question is if it's worth it.
I hope this helps you!
Andrée Starå
Workflow Consultant @ Get Done Consulting
I want to push the latest status log sheet entry to the dashboard. I have added working columns for the last date, recent value (0 or 1) and recent status (text field). The recent columns are blank except for the most recent data rows (that part of the sheet is working). I have a project metric sheet template across topics…
Hi - I am trying to figure out how to create a SUM of the Total Project Time aligned to each PM for all of their projects. On my master sheet I have the Resource Type, Resource Name, and a Helper Column for Time. The Helper Time is an estimated allotted time based on the timeframe of the project. Example: <3 months = 25…
I am looking to count how many letters we have issued within each month, this is by going by the modified date, these are the formulas i have tried as i want to start this from August: =COUNTIFS(Modified:Modified, MONTH(@cell ) = 8, Modified:Modified, YEAR(@cell ) = 2025) However, it comes up with an error. Any ideas…