Hi, we are planning a home construction project and are not sure of dates. Is there a way just show days without dates, and exclude Sat/Sun?
Hi,
You can plan out the project and only begin with using the duration column, but it will not show a Gantt chart (I think that´s what you're after?). You'll have to have start and end dates to be able to show the information on a Gantt chart.
Regarding the exclusion of Sat/Sun. You can set that up in the Project Settings - Dependency Settings in the Gantt view.
I hope this helps you!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I'm trying to create a graph chart that captures monthly count of records by divisions (Northeast, West and Central) that should be stacked with a legend displaying each by different color like a presented in Excel. When I attempt to duplicate the process in Smartsheet I receive the following results. In Excel, I created…
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…