Hi,
I want to create the gantt with schedue as below:
Task A
Subtask A1 Oct 15 to Oct 19
Subtask A2 Oct 15 to Oct 19
Subtask A3 Oct 22 to Oct 26
Subtask A4 Oct 29 to Nov 2
Predecessors of A3 = Subtask A1 and Subtask A2
Predecessors of A4 = Subtask A1 and Subtask A2
Subtask A3 and Subtask A4 are assigned to the same resource and the resource is expected to start with A3 first and A4 later.
However, SmartSheet does not support this input and result an error when I amend the start date of Subtask A4 to Oct 29.
Is this is the "constraint" of Smartsheet on this? And why?
Thanks and regards
Frank