Hello,
I need assistance with creating a formula to look at the end date and % complete columns. If the end date is nearing and the % complete is less than 100% the corresponding RYG should appear. The durations of each task varies from 1 day to 100 days depending on the project phase. What formula do you recommend for the formula to look at the end dates and % complete columns? Because the duration time varies - is there a universal formula I could use to look at the end date and % complete columns?
The specifications are:
Red: if the % complete is less than 70% and the end date is nearing 10 days out (today plus 9 days)
Yellow: If the % complete is less than 60% complete and the end date is nearing 15 days out (today plus 14 days)
Green: If the % complete is greater than 70% and the end date is greater than 15 days out
I look forward to your assistance. Please let me know if you have any questions.
Thank you!
Sara