Need help with formula to calculate end date with % complete.
Hello,
I need assistance with creating a formula to look at the end date and % complete columns. If the end date is nearing and the % complete is less than 100% the corresponding RYG should appear. The durations of each task varies from 1 day to 100 days depending on the project phase. What formula do you recommend for the formula to look at the end dates and % complete columns? Because the duration time varies - is there a universal formula I could use to look at the end date and % complete columns?
The specifications are:
Red: if the % complete is less than 70% and the end date is nearing 10 days out (today plus 9 days)
Yellow: If the % complete is less than 60% complete and the end date is nearing 15 days out (today plus 14 days)
Green: If the % complete is greater than 70% and the end date is greater than 15 days out
I look forward to your assistance. Please let me know if you have any questions.
Thank you!
Sara
Comments
-
Hi Sara,
You could use a nested IF statement, comparing today's date to your due date and have it output the desired color. I made an example formula, but it doesn't account for projects that are nearing due date and almost done, or ones that are nowhere near complete and a long ways out. It fills anything that doesn't match your criteria with "Unknown".
=IF(AND([Due Date]1 > TODAY() + 15, [Percent Complete]1 > 0.7), "Green", IF(AND([Due Date]1 < TODAY() + 9, [Percent Complete]1 < 0.7), "Red", IF(AND([Due Date]1 < TODAY() + 14, [Percent Complete]1 < 0.6), "Yellow", "Unknown")))
Hope that helps! -
Thank you so much for the speedy response! I entered that formula and I'm receiving #unparseable. Any ideas?
Thank you,
Sara
-
You're welcome! Can you post a picture of the formula itself? I'll see if I can help out.
-
Here you go and thank you. I took the 201 class with Lauren yesterday and forgot to ask her about this formula.
Thanks,
Sara
-
No worries! you just need to change the column names to match yours, that should fix it.
-
I think we're getting close. Any ideas why I'm returning unknowns? I was hoping to make sure the RYG appears on the status column.
Basically what I'm trying to track is the % completes and the estimated end date. I know it's a little tricky because of the different durations.
I appreciate the speedy response and help. Thank you!!
-
Those ones don't fall into the criteria since they're already complete, I wasn't sure what you wanted ones like that to appear as so I didn't account for it in the formula. I set it so anything that didn't meet the criteria appeared as "Unknown", would you like them to be green circles or say complete?
-
Thank you so very much! I think I got it. Thank you again!
-
You’re welcome! Happy I could help, I hope you have a nice day.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!