I need help moving a project that has predecessors. This is being used for a production facility to track the status of our projects. However, I have run into a problem when needing to move a project in the order of production. The predecessors are not moving with the project change.
-I need the "Design" process of the next project to start one day after the "Design" process of the previous project ends.
-I need the "Caseworks" and "Millworks" of each project to start once the "Design" process of its project ends.
-I need the "Finishing" of each project to start 1 day after the "Caseworks" begins.
-I need the "Hardware" of each project to start 1 day before the "Finishing" ends.
Is there anything I should be doing to make this happen? Smartsheet1 is a screenshot of it before the move in production schedule. Smartsheet2 is a screenshot of it after the move in production schedule.
Thanks for any help you can give. Betty