For some reason the dateline in Gannt view is not showing in my PDF outputs.
The same result in both print and export.
Is there a setting I am missing somewhere to make this visible?
Hm, must have been dreaming the last time I printed a pdf of the gannt view.
It seems that there is no way of including the date line in a pdf if I read posts from before. The last entry I can find about this is from the beginning of 2017 and I suppose there has not been any changes in two years..
This brings up another question, is there anywhere to see what features actually been worked on? Roadmap?
Hi Mattias,
Unfortunately, there isn't a public roadmap anymore.
The only way to be aware of things to come is if Smartsheet tells about it in the community or thru the EAP (Early Adopter Program)
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Ok, thanks. A pity to not see what is going to happen with Smartsheet in the future.
Regarding the missing date line and a possibility to have that visible in a PDF export, is this something that I am missing in the settings?
I'm always happy to help!
Regarding the date line, I think it's not included because when you export or print it will not show the correct (today's) date in the future. It's not dynamic.
Make sense?
Andrée
I understand your argument, but it would be a nice thing to be able to add the dateline as a timestamp when the pdf was printed as an option.
People are still scared of entering into the dynamic world of sharing...
Yes, that makes sense as well.
I advise my clients to add the date/time stamp to the export or printout so that everyone involved knows when the information was correct.
One workaround could be to export the pdf and add the dateline inside another solution.
Another possibility is to export the sheet and import it to a Gantt solution that can have the dateline /today mark present. Office Timeline / Pincello is a great solution for this.
Would that work?
I have run into an interesting but small bug. When setting up an automation, the action 'change cell value' will allow you to select checkbox columns, but not checkbox columns that are the star or flag visual variant. Those can't be selected in the change value action. Now the real issue. I go to submit a bug report or…
Hello All, I am having difficulties uploading my information to the welcome and help screens. We are a Micro Soft 365 shop, using share point, and I am getting the error message that share point in refusing to connect. Whereas this appears to be a share point issue; I have reached out to our IT Department, and we cannot…
Hi Everyone, I am managing a pipeline tracking sheet, and there's one intake form and one dynamic view connecting with this sheet. For the column "Branch Contact" and "Sales leader", I set the filed type as "Contact list" and the validation as "No validation". Once I input the username in the intake form, I go to the…