Sign in to join the conversation:
Just encountered the hard limit of 20,001 rows when exporting a report to Excel, Took me awhile to figure out what happened. Just wish there was a simple prompt to alert me to the issue. 20,001 is a bit low in my opinion.
Hi Mike,
This might help.
Please submit an Enhancement Request when you have a moment.
Only the first 20,000 rows will be included in the Excel document.If your report has more than 20,000 rows, create multiple reports that pull in fewer rows and export each report as a separate Excel file.NOTE: If a sort was applied to your report, fewer than 20,000 rows may be exported.
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I have imported a fillable PDF form and have moved over all of the corresponding tabs. When I hit save to generate the form it get the following: To generate documents, please add some content to your sheet. Any ideas?
Hello, Our Task Tracker sheet is used to manage and collaborate on internal tasks. Each team member received a daily email containing all tasks assigned to them, and we all LOVE the update request feature where we use a webpage that resembles a form to review & update each request, click next, go through all tasks, and…
This is what I would like to accomplish using Smartsheets but I am struggling to find the best way to go about it. Each year we get new vegetable varieties that we need to test in various locations at different times. I would like a tool that I can follow each variety up with a grower. The following data is added:…