I have en alert when start date is in 14 days.
But in the notification i only see the sub task row and not the main task.
Hi Maurits,
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? That would make it easier to help.
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hey A,
I would like to see also the "Stage 3: Rose Garden" when i have alert on end date.
Now i only see the "productie" so i can't now witch stage it is.
Ok.
That's weird because you are supposed to see the Parent as well.
Can you upload some screenshots of the rule in Alerts & Actions and I'll take a look to see if I can see what could be wrong.
Andrée
Check attached
Thit you checked my attachment
Can you also share a screenshot of the email message from the Alert that you receive?
How did it go? Did you get a solution to your problem?
Andrée Starå - Workflow Consultant @ Get Done Consulting
My company uses Smartsheet on an extremely rudimentary level. We are not tech savvy; we are tragically behind. We have only figured out to use one automation so far, which is when a new cabinet-related "project" gets automatically added to our "Active Projects" sheet from our "Sales Pipeline" sheet. But we have a major…
Hi Smartsheet community! I am looking for guidance on best approach to create an individual tactical plan w/ embedded milestones and general timeline that rolls up into a Team tactical plan w/ milestones/timeline. Hoping for functionality where individuals are notified a milestone dates and progress to goal is tracked at…
Hi there, I am attempting to use Smartsheet for meeting agenda planning. I have a sheet to house the meeting agendas and would like to be able to copy/paste the cells with the agenda items and their details to microsoft products for sharing across teams. It seems the only way to copy text from smartsheet is to highlight…