I have two sheets, one sheet is linking from the other on whole columns.
Is there a way to automatically include information that is added to the sheet (additional rows) to link to my other sheet?
Have you tried using DataMesh instead of cell linking?
I have not used DataMesh before, so I can't speak to that. Without it cell linking will not auto-populate new rows. The only option for displaying new rows would be to use a report.
What kind of data are you displaying and how are your sheets laid out? We may be able to help with another solution.
Hi,
How is the new data added to the sheet?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
We had a licensed user delete several files before leaving our organization. All of the sheets he owned have been transferred to someone else. However, there was one form we could not retrieve - Themed/Research Session Submission Form. Is there a way to recover that form? Any help is appreciated. Beverly Vance AMATYC…
Is there a way to save as a backup all sheets and workspaces? I am able to create a backup for all of the files shared with me. As the account's admin, can I back up all of the sheets and workspaces by all of our licensed users - even if they are not shared with me. We recently had a licensed use delete sheets and…
Hello all, I have a weekly report that I'm building and would like to be able to only expose two weeks worth of status. The report has a status and a commit date column and I'd like to remove anything that is "Done" and more than 2 weeks old. I'm trying to avoid having a report that has 100 rows of tasks that have been…