Hi,
Can someone help me on this formula.
Please check the formula if the % is greater than 100 % its should shows as Yes but in my formula its showing as No.
Hi Jimmy,
It will work if you change the 100 to 1.
Smartsheet looks at the numbers in a column formatted for percentage (for example, a % Complete column) as values between 0 and 1. Use decimal values (examples: 0.25 for 25%, 0.5 for 50%) to get the correct comparison, as opposed to whole numbers.
Did it work?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Awesome..Thanks Andree
Happy to help!
Andrée
I have seen this question asked multiple times in the forum, but I couldn't find any clear answer provided in the answers. Please excuse me if a solution already exists, but if not, will someone please let me know if it is possible to use a previous cell value (from cell history) in a formula? I am specifically trying to…
I have an automation set up so that when the Status column changes to Complete, Canceled, or Not Needed, Smartsheet automatically updates the % Complete column to 100% (Text/Number column type). After that, another workflow should trigger to alert the next person that their task is ready. This worked fine before, but…
Happy Thursday. I know many have asked this question before, but does anyone know of a way to have a column actively countdown time? Even if a plugin is needed, it will be considered. Here is what I'm looking to do. When a form is filled out and a new line is added to the sheet, I'd like the "Countdown Timer" column to…