Trying to use the =dateonly to get the variance between planned start and actual start, but it looks like the calculation is counting the weekend days when in only want it to count weekdays. Is this possible?
The networkday function should help with this use case. You can read more about this and our other functions here.
I think that is working, thanks so much!
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…