Trying to use the =dateonly to get the variance between planned start and actual start, but it looks like the calculation is counting the weekend days when in only want it to count weekdays. Is this possible?
The networkday function should help with this use case. You can read more about this and our other functions here.
I think that is working, thanks so much!
I have existing sheets, reports and dashboards I would like to rename. I am going into the sheet etc. selecting file, rename, renaming and then clicking out of the name box. it appears to have worked. However, when I go back to browse the file reverted back to the previous name. I'm not sure what I am doing wrong.