Hi,
I've got a GANTT chart with dependencies, so if a task is delayed / time is added it will have a knock on effect to all other tasks along the critical path.
One thing I'd like to add is a 'holiday block' where during the month of February nothing is actioned. If a task falls over February, I'd like it to be split.
eg: If a 2 week task starts during the last week of January, it'll work up until the start of Feb, then halt, then restart for the final week in the first week of March...
Is there an easy way to do this?
I've followed the below instructions, but I can't see any pink holiday days...?
https://help.smartsheet.com/articles/516392-defining-working-non-working-holidays-on-a-project-sheet
Thanks,
Richard