Hi!
I have 7 columns that have check boxes. When all 7 columns in one row are all checked, I would like a column that will auto populate a "completed" date. Is this even possible or am I insane? haha! Thank you!
This is not currently possible without a third-party solution like Zapier. There is no date-stamp option in Smartsheet although it is a HIGHLY requested item. I recommend that you submit a product enhancement request to add your vote to their list.
There is a possibility of adding a Modification date system column to your sheet, but anytime something changes on the row the modification date would change too.
Hi,
It's possible, but you would need to use a third-party tool like Zapier or similar.
Would that work?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…