New smartsheet user here. I really like it!
However, I need a way to change working days on a task level. Is this possible?
For example, I have "cure time" for concrete finish work. The time is continuous regardless of holidays and non-working days. The concrete just sits and cures. Nothing else needs to happen. Unfortunately, if cure time lands on a holiday, the gnatt chart will show one additional day. If I then change the "duration" to account for the holiday, I wind up having to recheck it each and every time a predessor is modified. This is tedious and dangerous in my line of work.
Seems like there should be a simple fix? Is there?
Other than that, so far it's awesome.