How does linking work?
Hello,
I am new to the Smartsheet world and I just started using this for my projects but I do have a question on how the linking works. I tried linking several project schedules into one integrated plan but everything I was changing on the master, was changing the original plan. Is this a true statement? Or am I wrong and need to go back and look into this more closely?
Thanks,
Comments
-
Hi,
You can link in both directions, but a typical scenario is to link to a master schedule from all projects.
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? That would make it easier to help. (share too, andree@getdone.se)
Hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 143 Just for fun
- 58 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives