How can I establish a baseline in smartsheet?
I am using smartsheet for construction scheduling. Like many industries there are delays. However, in construction delays come with a cost, a dollar amount that needs to be paid when projects go over their time line.
I establish my schedule when I start a project. Throuhgout the project there are delays, rain days, missing information, people don't show up etc. I need to attribute each delay to a particular indiviual or cause and show how the delay moved the schedule.
In a lot of scheduling programs there is a basline, the original schedule. This gets locked in at the beging. As the schedule changes, there is a second line the developes in the gant chart which shows how the schedule is changing and there is a note you can attach to each change.
How do I show the baseline in smartsheet, and show the changes as they occur with notes?