Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
How can I exclude a task(s) from my report if the predecessor for that task is not complete?
I have a dozen or so proejcts each with their own sheet. I've created a simple report that looks at each project and returns tasks that meet two criteria:
1. The task has not been marked complete
2. The task has a due date of 5 days or less.
This report works fine, but it returns more data than I want to report on. Specifically, it reports on tasks that are dependent on other tasks being completed. I only want to report on the first task (earliest due date) in a chain of dependent tasks.
Thank you,
Tim
Comments
-
Hi Tim! Reports are designed to bring in rows based on criteria in a single row.
In your sheet, you could build a formula that checks the row above for completion (this would work if your tasks are in sequential order and you dont sort/rearrange).
The formula could look like this (located in row 6):
=IF(Status5 = 1, 1, 0)
This checks the status on row 5 (flag column) and if the task is complete (flagged) then the formula displays a 1. If the task is not complete, it shows a 0. This criteria could then be used as a report criteria.
-
For me the same problem. But if I have done like you recommended I can not build the report correctly.
Because
1. Status must be NOT completed
2. Status of predecessor task MUST BE completes
If I make a report like this only the rows are showed which status NOT completed AND (or OR) predecessor task MUST BE completes. But i Like to have a repport wiith both
So I like to have in the report
Rows which not completes but IF there is a predecessor task than only if the extra collumn shows a 1 (predecessor task is completed)
How can I build that report?
-
Judith, there would have to be something in your row that indicates the predecessor is completed. You could use a formula to check a box or set a status if the predecessor is complete - then use this in your report. This would be easy if all your rows/predecessors were consecutive but would take a little longer to set up if they are not.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 412 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 138 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives