Hi there,
Is there a way to have a task start on the next day, regardless at what time the predecessor finished on the day before? So like a adjustable lag day (or hours) if you want.
Thanks!
If you are on a project sheet the in the predecessors column type the row number of the task you want it to be after then add one
2 + 1
If you are in a grid sheet reference the cell with the date you want to follow then add one
[End Date]1 + 1
Circling back to this….. Another year goes by and still no folder level sharing. Smartsheet developers don't listen to their clients. I have seen hundreds or posts and requests for this over the past 7-8 years. And still NOTHING!! This has been a huge issue for us as a company. As you can tell this is a sore spot for us…
Today a team member accidentally changed several rows by either deleting the data or the row itself. Do I download a snapshot of each one to restore? Some of them didn't seem to be too helpful. What is the protocol for restoring this information? I've only done this before with the help of a representative and it was…
I have my Smartsheet set to generate a document when a form is filled out. The document is a fillable PDF and when the document generates not all of the answers populate on the generated PDF. I have tried making the PDF again from scratch, I have tried copying and pasting the fields so I know they're the exact same…