Start task next day

pixelsmart
✭✭
Hi there,
Is there a way to have a task start on the next day, regardless at what time the predecessor finished on the day before? So like a adjustable lag day (or hours) if you want.
Thanks!
Comments
-
If you are on a project sheet the in the predecessors column type the row number of the task you want it to be after then add one
2 + 1
If you are in a grid sheet reference the cell with the date you want to follow then add one
[End Date]1 + 1