Is there a way to have a task start on the next day, regardless at what time the predecessor finished on the day before? So like a adjustable lag day (or hours) if you want.
Thanks!
If you are on a project sheet the in the predecessors column type the row number of the task you want it to be after then add one
2 + 1
If you are in a grid sheet reference the cell with the date you want to follow then add one
[End Date]1 + 1
Hello, I'm working through the writing formulas optional activity and in the 'Nested IF function - Progress Column' task it directs you to put in the following formula '=IF([% Complete]@row = 0, “Empty”)'. However, when I put this formula into the spreadsheet, '04a_Marketing Request Tracker - Formulas', I get an…
I have an automation that has a condition where I am looking at the column "LEA Interco Supporting Site(s)" and trying to find columns that have the value "Fort Loramie" in them. This works well when "Fort Loramie" is the first item listed in the cell, but it doesn't work when "Fort Loramie" is the second or third value in…
Have any of you created a Smartsheet that would show the savings for a project by the month? In other words, if I saved $1200 annually and the project ended in say March, then the savings would go $120 per month, Mar 2025-Feb 2026. I have done it on Excel sheets manually, but I think there should be a way to do it with…