I don't see an option for it in the "View" button for my project. I did find this article in the help pages:
https://www.smartsheet.com/pert-101-charts-analysis-and-templates-more-accurate-project-time-estimates#pert-analysis-how-likely-will-the-project-be-on-time
Which says "if you do it by hand" implying there's another option.
Please advise.
Hello—
Smartsheet has Gantt chart functionality, and as such, has critical path functionality: https://help.smartsheet.com/articles/1979152-tracking-a-project-s-critical-path
I understand that this is similar, but not the same as PERT. Currently, Smartsheet doesn't have functionality to build a PERT chart. When you have a moment, please submit an enhancement request using the form under Quick links to the right of the community site to let our Product team know that you'd like to see this capability added.
Hi there, I have just recently worked with Smartsheet's Implementation team to build a Control Center Blueprint. The workspace that holds the solution is titled something very generic and I would like to rename it. Can I do that w/out breaking anything or what steps would I need to take to successfully rename it. Thanks in…
Hey, I've got a sheet, which is autopopulated as a source sheet to feed into DataMesh (which runs once every 24 hours). Once DataMesh has run, how can I auto-clear the rows in the sheet to avoid repeating this the next day? I have no use to keep the data and want to avoid clogging up the source sheet. I have tried…
Hello everyone seeking for an answer and help please im having a hard time on approval request automation . My workflow runs smoothly however when the approver open the attachment on the request it automatically downloads and when clicking the approve it says link are already used and auto decline teh approval request…