I don't see an option for it in the "View" button for my project. I did find this article in the help pages:
https://www.smartsheet.com/pert-101-charts-analysis-and-templates-more-accurate-project-time-estimates#pert-analysis-how-likely-will-the-project-be-on-time
Which says "if you do it by hand" implying there's another option.
Please advise.
Hello—
Smartsheet has Gantt chart functionality, and as such, has critical path functionality: https://help.smartsheet.com/articles/1979152-tracking-a-project-s-critical-path
I understand that this is similar, but not the same as PERT. Currently, Smartsheet doesn't have functionality to build a PERT chart. When you have a moment, please submit an enhancement request using the form under Quick links to the right of the community site to let our Product team know that you'd like to see this capability added.
Hi everyone, My boss is bringing data in from my Smartsheets into PBI. He is having issues with the dollar value columns showing up as text instead of dollars. There is no option for the column except for text/number. What can I do to solve this problem? Thanks! Freda
How do I make a dashboard available so that anyone can access it without having to login?
I have a project tracking sheet that is updated weekly with the most recent updates for project progress, issues/concerns, barriers requiring intervention and next steps. How can I display only the most recent updates for these 4 columns in a dashboard?