I don't see an option for it in the "View" button for my project. I did find this article in the help pages:
https://www.smartsheet.com/pert-101-charts-analysis-and-templates-more-accurate-project-time-estimates#pert-analysis-how-likely-will-the-project-be-on-time
Which says "if you do it by hand" implying there's another option.
Please advise.
Hello—
Smartsheet has Gantt chart functionality, and as such, has critical path functionality: https://help.smartsheet.com/articles/1979152-tracking-a-project-s-critical-path
I understand that this is similar, but not the same as PERT. Currently, Smartsheet doesn't have functionality to build a PERT chart. When you have a moment, please submit an enhancement request using the form under Quick links to the right of the community site to let our Product team know that you'd like to see this capability added.
I'm trying to create a graph chart that captures monthly count of records by divisions (Northeast, West and Central) that should be stacked with a legend displaying each by different color like a presented in Excel. When I attempt to duplicate the process in Smartsheet I receive the following results. In Excel, I created…
Good afternoon, I am trying to utilize Linked Dropdown Columns for a manual process we have. We have many sheets that use a "Client Name" column with a dropdown list. Whenever a new client comes on or exits, we have to manually update every sheet that has a Client Name column and update the dropdown list. We do not have…
This should be straightforward information but I can't find it anywhere. How do the Automation triggers work for attachments? I assumed: An attachment is Added = New attachment An attachment is Changed = New version of existing attachment. But I just had an 'Added' attachment notification trigger when I uploaded a new…