I don't see an option for it in the "View" button for my project. I did find this article in the help pages:
https://www.smartsheet.com/pert-101-charts-analysis-and-templates-more-accurate-project-time-estimates#pert-analysis-how-likely-will-the-project-be-on-time
Which says "if you do it by hand" implying there's another option.
Please advise.
Hello—
Smartsheet has Gantt chart functionality, and as such, has critical path functionality: https://help.smartsheet.com/articles/1979152-tracking-a-project-s-critical-path
I understand that this is similar, but not the same as PERT. Currently, Smartsheet doesn't have functionality to build a PERT chart. When you have a moment, please submit an enhancement request using the form under Quick links to the right of the community site to let our Product team know that you'd like to see this capability added.
I have a public facing form and was looking to provide an automated response to the form submitter, but the submitter is not part of our organization/part of contact list. I would like to use the e-mail address they provide to send an answer. Hopefully with the document attachment that is created automatically through…
I want a formula that can reference updates on another sheet and add the info onto my sheet. The other sheet is a schedule that has job locations and PTO time for each individual on each day of the week. I want to know the dates that each individual on the sheet has an upcoming PTO, and for my sheet to update with 'PTO' on…
Hello! I am trying to create a form that everyone on my team can use to gather contact information from clients. The preference would be for each form submission to create a new sheet since each one would be for a different client. We found that Microsoft Forms will allow us to do this, but it doesn't look as polished. Can…