Hi there,
we have this issue in few smartsheet pages where assignment is not working properly. we assigned a person %10 (or any other percentages) to the work and no matter what we do, it shows %100.
Hi Leila,
Thanks for your post, I'm happy to help. Is it possible that the Allocation % column has not been set in the Project Settings? If this column has not been defined, Smartsheet will always default to 100%. To check this:
See the screenshot below for reference. More information about this can be found in the following links:
If you continue to experience issues, I recommend reaching out to our Technical Support team at https://help.smartsheet.com/contact
I hope this helps!
Isaac J
Smartsheet Support
I am currently setting up an automation for people to get notified through their email, when they are prompted. But is there a way that they can reply in the email of a comment that will then go to the specific sheet. This way they do not have access to the sheet, but can just comment through email with updates?
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.