Hi there,
we have this issue in few smartsheet pages where assignment is not working properly. we assigned a person %10 (or any other percentages) to the work and no matter what we do, it shows %100.
Hi Leila,
Thanks for your post, I'm happy to help. Is it possible that the Allocation % column has not been set in the Project Settings? If this column has not been defined, Smartsheet will always default to 100%. To check this:
See the screenshot below for reference. More information about this can be found in the following links:
If you continue to experience issues, I recommend reaching out to our Technical Support team at https://help.smartsheet.com/contact
I hope this helps!
Isaac J
Smartsheet Support
How can I delete old sheets I no longer use from my account?
I'm trying to display a task progress chart showing "complete", "late", and "not complete" in my dashboard and for some reason the chart will display as a column chart but it won't display as a donut chart even though I'm referencing the same report. I'd prefer to display as a donut chart as I think it looks better and is…
Hello, I am trying to create a chart widget in my dashboard, but I keep getting "Selected data cannot be charted. Please select a new range." error. The report I am using is already summarized in numeric value. What is funny is I have report that I created a chart widget in another dashboard, and when I use that same…