% Complete staying 0
Answers
-
Additional Information:
I just found out that if I change all the children to 100% then the parent gets changed to 100%. If any of the children are not 100% then the parent is 0%.
-
Hi Don,
Have you activated the % Complete feature in the project settings?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
I believe that I have
-
Thanks for pointing me in the right direction. I turned off the dependencies and the options in the project settings. Saved the sheet. Reopened the sheet, and set the dependencies. Saved the sheet. Reopened the sheet, set the options, and now the rollup works for the % complete.
Thanks again for your direction.
-
Excellent!
Happy to help!
Best,
Andrée
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
I have the same issue and performed the suggested steps (quoted above), but no change. Interestingly, some of the parent rows DO calculate % complete correctly based on the child rows - some of the parent rows DON'T. Any suggestions?
Thank you!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.1K Get Help
- 348 Global Discussions
- 199 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 133 Brandfolder
- 127 Just for fun
- 127 Community Job Board
- 455 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 282 Events
- 36 Webinars
- 7.3K Forum Archives