Task end date as a function of resource availability
Hi community,
I'm seeking to calculate a task end date as a function of resource availability.
Say a task completion depend on a resource availability and productivity. How can I calcualte a task end date given a resource availability.
Here's a simple example to illustrate :
Task : Writing a 1000 pages documents
The task is assigned to a writer with a 10 pages per day productity.
How can I calculate the task end date, taking into account any period of the resource will not be dedicated to his/her task. (holidays, training etc.).
I hope that is clear. Best.
Thanks,
Comments
-
You can't use a project sheet and do this, but it can be done. Project setting make it so you can't use formulas on start date end date duration or predecessors.
The words to explain how to do this escaped me, so take a look at this and see if it helps you.
https://app.smartsheet.com/b/publish?EQBCT=9efd19e412724fdeba466a9301afdb08
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.2K Get Help
- 360 Global Discussions
- 198 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 136 Brandfolder
- 127 Just for fun
- 128 Community Job Board
- 444 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 283 Events
- 35 Webinars
- 7.3K Forum Archives