When I export the gannt chart it is missing the arrows that link predecessors which I can view in my project sheets. Is there a way to get the export to show the same thing?
Thanks,
Amy
Hi Amy,
If you export to PDF or as an image, it will be included, but it won't work if you export to an Excel sheet because Excel can't show that information.
Hope that helps!
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hello,
You may find that some of the exported data may not appear as it does in Smartsheet. For example, both Microsoft Excel and Google Sheets do not support gantt charts or certain column types like the Dropdown, Contact, Checkbox, or Symbols columns.
If needed, more information on exporting can be found in our help article: https://help.smartsheet.com/articles/770623-exporting-sheets-reports-from-smartsheet
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…