I purchased the Office Timeline + package and love it. The one question I can't figure out is the following. Use case: I import a project schedule into timeline--select the tasks that I want displayed--and I adjust all the formatting. Then two weeks later, one key task changes duration and/or start/end date and it adjusts my entire project plan because of the dependencies. My goal is to re-import in the schedule and only have it update the dates in the tasks and keep all the same formatting, and only display the tasks that I previously selected. It appears that a new import is just that--new and I have to start from scratch. Any ideas? Thanks!