i have tasks a,b,c - all tasks are 2 days in duration
task 'b' is dependent on 'a', and task 'c' id dependent on 'b'
task 'a' was scheduled to start on 1/1/16, but it was started earlier and so it was marked complete on 31/12
how do i set it up so that task 'b' now slides along to 31/12 showing it is available to start, and equally how task 'c' slides along to its start 2 days after the new start date for task 'b'?
Can anyone help please
Thanks