When a task is complete ahead of schedule the dependent tasks start date is not brought forward

Alan Russell
edited 12/09/19 in Archived 2016 Posts

Hello

 

i have tasks a,b,c - all tasks are 2 days in duration

 

task 'b' is dependent on 'a', and task 'c' id dependent on 'b'

 

task 'a' was scheduled to start on 1/1/16, but it was started earlier and so it was marked complete on 31/12

 

how do i set it up so that task 'b' now slides along to 31/12 showing it is available to start, and equally how task 'c' slides along to its start 2 days after the new start date for task 'b'?

 

Can anyone help please

 

Thanks

 

Alan Russell