Repeating the same task across multiple months

HB
HB
edited 12/09/19 in Archived 2016 Posts

Hi

 

I am building task lists for our global team for the rest of 2016 that I will be showing in a calendar view for them and setting up alerts and reminders on what has to be completed, when.

 

I have a number of tasks that need to be perfomed every month; how do I set these up to repeat?

The only way I can think of how to do this atm is to create different lists for each sub tasks for each month:

 

June

  • Finalise data
  • Produce reports
  • Sign off data from senior mgmt

 

July

  • Finalise data
  • Produce reports
  • Sign off data from senior mgmt

 

Is there  a more streamlined way  to do this?

 

Thanks

Comments

  • J. Craig Williams
    J. Craig Williams ✭✭✭✭✭✭

    HB,

     

    An option is the row Update Request.

    I've had limited success with this primarily due to the UR being a one time link.

     

    The UR goes to the person and they update the row to "reactivate" the row as a task.

    They  use their task list as normal, now that the task is back on the list.

    When they finish, they update / complete the task.

    When the cycle comes around again, they get the next task to "reactivate" the task.

     

    So, I wasn't using the UR to get a status update, but rather to create the next task.

     

    Hope that is clear.

     

    Craig

     