How can we calculate time between start date and finish date? I want to know by hour and minute format?
I built this a while back.... read comments for the formulas
https://app.smartsheet.com/b/publish?EQBCT=698fa97db2e848acbba1db03ca04667b
Thank you for sharing this but is there any automated format or formula to calculate time without manually entering by users?
Nothing built in at the moment.. I believe some use Zapier to grab a Modified Date and hard-code it into a cell every time something specific happens.
Ezra is correct!
Zapier is a great option for this scenario. Is that an option for you?
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I tried using Zapier but how? Zapier wants me to buy timecap app as well.
Azuqua seems pretty promising but my company doesn't want it since they think it might compromise the security.
What do you mean with that Zapier wants you to buy timecap?
Azuqua was excellent, but they have been acquired, and it's being retired for external use.
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…