I've done some research, so I'm pretty sure I already know the answer. I have a project with a hard completion date. I would like to have any subtask scheduled backward from the completion date. Can that be done in Smartsheet?
Hi,
There is a Template called: Project with Hard Deadline and Gantt that probably is what you´re looking for.
Hope that helps!
Did it work?
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Andree,
Please enter the link for this Template or information you found. Your comments are useless to everyone searching. This is not the best website for searching and finding correct answers at the top of the list. On these community boards we need to be accurate in the links to point people in the right direction. Thanks.
At the time of my post, I don't think it was possible to link to the templates but now it is so here you go:
https://app.smartsheet.com/b/home?sc=mjjH3-k10qQ%2Cm9FH33U15fo%2C1
I hope that helps!
Workflow Consultant / CEO @ WORK BOLD
This Template is located in the SOLUTION CENTER
Go To Solution Center
Enter Search : Project with Hard Deadline
You will see the Single Project Template Called
"Project with Hard Deadline and Gantt"
Click on it and it will appear in your SmartSheet Collection
Not much to look at but at least it can start a person in the right direction for entering a Deadline Date and the remainder of items get scheduled using predecessors with SF with task below.
My link above is the direct link to open a copy in your account.
Here's a link to the Solution Center page with that specific template.
https://www.smartsheet.com/marketplace/templates/project-hard-deadline-and-gantt
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…