Sign in to join the conversation:
Hi There,
Apologies if this has been addressed elsewhere, I could not find anything similar.
Are you able to status update a programme so to update % complete and the resequence the programme task to start after the today line?
Hi,
Not sure I follow!
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help.
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
With a construction programme as you progress through time you update an activity based on progress achieved. i.e. % complete. If you have an activity/task that was due for completion yesterday, but the activity progress is only at 80% complete, then this means the remainder of that activity needs to be rescheduled to start after today.
Most construction planning and programming software has the ability to "schedule" or "update" the programme where uncompleted activities are moved to the right i.e. to start after the schedule date.
Refer attached snapshot where I have tried to demonstrate what i mean.
Is there an answer to this?
Hi, For some reason, using sort dates, my report has put January 2027 before any 2026 dates? Conditional formatting it set up to be red if not complete and past date, hence the 2027 row being the only white. Thankyou in advance!! :)
I create an Automation that alerts someone after criteria is met. Everyone is not receiving the email. Automation is also set to unrestricted. Any ides what could be happening here?
When I access the activity log - it shows everyone who has accessed Smart Sheet in a specific Timeframe. Is there a way to filter to only show people who have accessed it that are in my Internal Organization? I tried using the collaborator field but it only lets me put in my email. When I put in other team members email…