I have the start day and the duration. Is it possible to calculate the end date using these two entitites such that only working days are included (only monday through friday and not the weekends)?
Thank you
I would take a look at the WORKDAY function.
WORKDAY()
WORKDAY(date, num_days, [holidays])
Used in a Date column to return a date from a specified number of working days. Optionally excludes holidays outlined in a range.
Hmmm. You might also try turning on dependencies. It will set up a start time and a finish time column if you don't already have one and calculate the finish time for you. When you edit the start date or the duration, the end date will calculate for you automatically.
That might be a better way of doing it rather than using custom formulas.
Another added benefit of turning on dependencies is that you can also make the end of one task determine the beginning of the next one.
Thank you very much.
It worked!
Happy to help!
I would also suggest looking into dependencies as Mike suggested below. I don't use them for various reasons, so I never think about them as a solution.
Can this be done without using a function?
I have a workspace that I created with two subfolders. A user needs to have access to only one of them but when I have that folder selected, I can only share the entire workspace with them. Is there a secret way that I can share the parent folder and ensure that any new files created will be shared with the same people? I…
I have a Pro plan but I cannot create ANY reports. The system does not allow me to choose a folder, and consequently a sheet to create a row report and suggests an upgrade to Business or Enterprise. I'm quite new to Smartsheet and feel a bit disappointed with this limitation, or maybe I'm just doing something wrong. Alberto
I have multiple items that each have their own statuses and that roll up to "workstreams" or swimlanes. On the dashboard, I would like to show the progress of the items by swimlane without breaking it out into separate widgets for each. This would ideally be a stacked bar where each bar represented the Items and was broken…