I'm trying to setup a project plan for when a task is marked 'complete' it auto-fills the 'Finish Date' column. Would I use an If, then formula? If so, what would that formula look like?
Thanks!
Crystal
Hi Crystal, this functionality is not currently available without using a third party tool like Zapier. We reverse-engineered our process to have the person enter a date and then have the status update accordingly.
Thanks, Mike! This is helpful. I'll try that approach.
Sounds good. Let me know if you have any questions! We created an Actual Start and an Actual finish date field to measure if the task was in progress or complete and changed the dropdown field with an IF function based on the dates being populated.
I've got the following formula in a Check Box column to check when something is due in the Next 3 weeks. =IFERROR(IF(AND(WEEKNUMBER([Projected Cleaning Date]@row ) = WEEKNUMBER(TODAY()) + 3, YEAR([Projected Cleaning Date]@row ) = YEAR(TODAY())), 1), "") I have them for 2 weeks, 3 weeks, 4 weeks, and 5 weeks. These stopped…
I'm using salesforce connector to pull my team's hours information in real-time. The Salesforce connector sheet contains sheet summaries that I'd like to use a cell reference for a different sheet. I can't seem to find the best way or formula to do this. I don't want to use a dashboard with report widgets because I prefer…
I have two formulas which work well independently, but when I combine them they don't. formula 1: =IF(YEAR([Joined date]@row ) = 2025, JOIN(COLLECT({Membership Survey 2025 - Experience}, {Membership Prioritisation Survey 2025 - Org}, [Organisation name]@row ))) formula 2: =IF(YEAR([Joined date]@row ) < 2025,…