Importing Rules with Gantt from MS Project
Hi there!
I imported my gantt from MS Project straight into Smartsheet but the end dates seem to be off by quite a bit, it isn't copying exactly in as I need it to. I then realised that have some rules in my MS Project that may not have carried over to my sheet.
So currently in my MS Project gantt I have rules applied for dates so that they include our work holidays and annual holidays. How to I get those to carry over to smartsheet?
Comments
-
Hello,
Due to the difference in functionality between both applications, some Microsoft Project functionalities —like constraints— are lost when importing into Smartsheet.
Since Smartsheet doesn't currently support constraints, I'd recommend submitting a Product Enhancement Request to let our Product team know that you'd like to have this functionality in Smartsheet.
If needed, more information on project settings can be found in our help article: https://help.smartsheet.com/articles/765755-modifying-project-settings
-
Thank You
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.5K Get Help
- 402 Global Discussions
- 213 Industry Talk
- 450 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 135 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 296 Events
- 36 Webinars
- 7.3K Forum Archives