Is there a way to create an alert based on numerous dependencies? For example, if Bill Smith needs to be notified only when both tasks 1 and 2 are complete, is there a way to do this?
There is, but it can become tedious depending on your exact details. What is the maximum number of dependencies for a row? Do you have lag/lead time built in? Are there varying durations such as days vs weeks vs hours?
No lag/lead time. No varying durations. Not sure how many dependencies but not a ton.
Ok. OS to start you would need a row id column that basically duplicates the row number. Then you would create a number of helper columns. 1 for each predecessor. You would use these to parse out your predecessors. Then you would create an additional helper column (checkbox type is easiest to work with in my opinion). In this checkbox column would be a formula that looks at whatever column you use to mark a task complete, searches for each predecessor, then checks the box once all predecessor rows are marked as complete. You would then use this final checkbox column to trigger your notification.
Does this sound like something you would want to tackle? It can become tedious and time consuming setting it up, but once it is set you can use the "Save as new..." feature or save the sheet as a template to be able to use it over and over again.
Honestly though... If it is one time use and a short lived project, it may not be worth the hassle of setting up.
Does it sound like something worth exploring?
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…