In Sheet One, there are 25 products assigned to 4 Product Types. Each Product has an expected delivery and an actual delivery date.
In Sheet Two, we want to add the dates associated with the percentage complete.
The existing formulas provide the percentages and totals but how can I add the dates for the milestones. For example, what is the date that 25% of Product Type Three was delivered. It should be:
25% Delivered = 10/14/19
50% Delivered = 10/15/19
75% Delivered = 10/17/19
100% Delivered = 10/18/19
Thank you for your help.