I'm new to smartsheets and it seems like a lot of the requested features go ignored.
Is there really no way to link a dropdown in a form to another sheet with source data?
This has been requested for years.. Maybe i'm missing something.
Hi Jlab, no this is still not available as far as I am aware. We have a simple API app which keeps one or more drop down lists in sheet/s upto date with drop down lists in other sheet/s. This would ensure your form drop-down list is always upto data with the source data it needs.
Let me know if you are interested in knowing more
cheers Dan
solutions@projectplanservices.co.uk
Howdy, I am working on developing a several dashboards for our team, and for whatever reason the widgets I place are multiplying. I have copied/pasted some, but other I have just added I am ending up with dashboards that look like this: When originally I only had the top four items. It has happened on several different…
I am a construction project manager and built sheets that include actual costs for individual tasks, departments and overall project. I update the costs cells as invoices come in by manually calculating then entering in new amount. Ex: Plumbing: week 1 $300, week 2 $250, week 3 $150 = $700. I enter $700 in cell. I'm…
I have multiple items that each have their own statuses and that roll up to "workstreams" or swimlanes. On the dashboard, I would like to show the progress of the items by swimlane without breaking it out into separate widgets for each. This would ideally be a stacked bar where each bar represented the Items and was broken…