I'm trying to enter a formula in a date field which is 10 days earlier than the date in another field. I read that I can perform calculations on date fields (https://help.smartsheet.com/articles/2477601-use-formulas-perform-calculations-dates) and reference another cell in the formula (https://help.smartsheet.com/articles/2476816-create-cell-column-reference-formula).
My formula is
=[Start Date]42-10
because I want the date that is 10 days earlier than the cell in row 42 of the "Start Date" column.
However, when I enter this formula in the cell and hit Enter, all I see is the formula itself. See attached screenshot. What am I doing wrong?
If the date column is assigned to either the start or end date columns and you have dependencies enabled in your project settings you cannot have a formula on it. These fields are calculated my SmartSheet based on the dependencies.
The project settings are accessible in the Gantt View via the cog (settings) icon under the Share button.
Frank is correct. It seems as if you have your dependencies enabled and are using that column as one of your project columns. You have a few options...
1. Disable dependencies in the Project Settings.
2. Create another column for the calculated dates.
3. Select a different column in your Project Settings.
4. Add lag/lead time if establishing predecessors.
Thank you, Frank and Paul!
Happy to help!
Date Report Partner CBO Name 01/12/25 Children's org 05/15/25 Foodbank 08/30/25 Children's org 09/11/25 Chamber 11/25/25 Digital Bus 08/21/24 Digital Bus South 01/15/26 Children's org 01/12/24 Foodbank Sister 02/15/24 For the children org 07/01/26 Digital Bus #2 08/05/26 Family Center 12/01/26 Family Center I am trying to…
I am trying to get the passenger count per month per year, and I can't seem to get the formula correct. I need to add the number of passengers for each month per year. If anyone could assist me with this, I would greatly appreciate it. Thanks!
I need to edit a large sheet that has a lot of predecessors. I need to delete one row and move another. when I make the changes the predecessors for proceeding lines are not correctly displaying the dates correctly. Need help.