Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Update requests with predecessors?
Hi all,
I am trying to send out update requests with Smartsheet with tasks with a predecessor, but the other user is not able to make a change.
I would have assumed that if someone needs to update the sheet, even with a predecessor on the task, this should show and allow for the change to be made?
Any help is greatly appreciated.
Comments
-
Hello Nico,
With dependencies enabled, End Dates of sub-tasks, as well as Start Dates of sub-tasks that are driven by a predecessor, aren't editable from an Update Request. This will also extend to Predecessors.
This is because these values are being calculated automatically by Smartsheet with the engines inside the app. When filling out an Update Request, you are looking at a static field which includes values from the sheet. It isn't able to make calculations when those fields are updated, as those can only be made within the actual app. This will also occur in Reports and on the mobile app.
I've added your vote to be able to edit dependency controlled cells in Update Requests to our enhancement request list to be reviewed by our Product team.
Let me know if you have any questions on this.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives