Hi community,
I'm looking for help on identifying milestone tasks that span multiple weeks (see screenshots below).
Our project plans have a "weeknumber" helper that checks the END date of a milestone task to set the week number.
I then use an Index/Match in the Summary Sheet area to identify the Milestone task name for the current week.
This works great when it is a 1 week task, but when a task spans multiple weeks, it returns “no match” when the end date is technically in the future (even though this task is in process currently).
A solution would be to add another weeknumber helper for START, and an IF/AND to the Index/Match in the summary sheet, but it seems that Smartsheet does not allow for nested Index/Match formulas.
I do also have a “Weekly Status” helper column that checks for start and end dates to report on current In Progress tasks. The only issue is that reports for ALL tasks for the week, not just the milestone task… But maybe that can be used somehow?
Any ideas are greatly appreciated.
